How can Irish Rail write off approximately €50 million of taxpayers’ money on a failed project, while passengers face higher fares and communities continue to struggle with inadequate railway services?
In 2020, Irish Rail awarded Spanish company Indra a contract to develop a modern train traffic management system. It was supposed to be operational by 2024.
Instead, after years of delays, technical failures and mounting costs, the contract was cancelled in July 2026.
The result? €50 million written off, no working replacement system, and the prospect of further expense.
Around €28 million went towards the contractor, with approximately €17 million spent on project management and associated costs. Irish Rail blames the contractor for failing to deliver. The contractor disputes this.
But who was watching over the taxpayers’ money?
Who approved the spending?
Who monitored the project?
Why was so much money allowed to be spent without a successful outcome?
Above are questions that Irish Rail’s senior management, its board and the National Transport Authority must answer.
And now passengers face another financial blow.
From January 2027, rail fares are set to increase, with Intercity Express fares rising by 10% and Economy fares by up to 20%.
The NTA says these increases are due to rising operating costs and funding pressures. There is no confirmed evidence that the failed €50 million project caused the fare increases. But taxpayers and passengers deserve to know whether they are indirectly bearing the financial consequences of this failure.
Meanwhile, communities throughout County Tipperary continue to struggle with limited rail services.
Imagine what even a fraction of that €50 million could have contributed towards improving rural public transport. Public money is not Monopoly money. It belongs to the people of Ireland.
We need a full explanation of what went wrong, who was responsible for the decisions, and what money, if any, can be recovered.
Accountability must begin with those entrusted to manage and safeguard public money.